Bypass navigation and go to content
Galt Sub looking West

Humber River Bridge

The Humber River Bridge is being expanded to accommodate four additional bridge spans and the current at-grade rail crossing will be replaced by a tunnel that will be built under the rail corridor crossing, providing a safer passage for Weston Golf and Country Club members.

Updates

  • April 29 – Work will begin in May to modify the tops of seven existing piers at the Humber River Bridge. Work on the west abutment is nearing completion with backfill and concrete pouring of the last level of the abutment. Once completed, new bridge spans will be installed on the widened portions of the piers and abutments in May.

Project Schedule

  • Advanced tree clearing of GO property on the west side of Humber River Bridge: March 2011
  • Construction start: April 2011
  • Construction complete: Spring 2014

What we are doing

  • Humber River Bridge
    • Bridge piers will be expanded on the north side to accommodate the additional tracks
    • The new span will effectively be double what it is today
  • Cart Path Tunnel
    • The tunnel will be built under the rail corridor crossing between holes 4 and 5
    • It will be suitable for all golfers and maintenance and will be designed to meet accessibility and safety features
  • Traffic - Installation of tie backs for the Humber River Bridge abutment structure will be installed. The nature of the soil is such that the presence of mud will be close to Weston Road. The right lane closure is to ensure safety of motorists during work.

How this will affect you

  • The construction schedule has been designed to minimize the amount of work on the Weston Golf and Country Club property during golf season
  • Crossing protection will be provided to safely escort golfers at the existing level crossing during construction
  • The landscaping will be restored to its current state
  • The 3rd hole tee box will be relocated
  • The new tracks will be continuous welded rail and the new spans will be ‘closed’ ballast decks for a quieter passage of trains

Noise and Vibration

Noise and vibration monitors have been set up along the Humber River Bridge project area to monitor any noise and vibration generated by the construction. This data will be posted on a weekly basis.

The following graph displays 1-hour averaged noise levels measured in decibels (dbA).

Humber River Bridge Noise Monitoring Graph

For a map of the station locations, please click here.

Archived graphs

2011 | January 2-March 31 | April 2-7 | April 9-14 | April 16-21 | April 23-29 | April 30-May 5 | May 7-12 | May 14-19 | May 21-26 | May 28-June 2 | June 4-9 | June 11-16 | June 18-23 | June 25-30 | July 2-7 | July 9-14 | July 16-21 | July 23-28 | July 30-August 4 | August 6-11 | August 13-18 | August 20-25 | August 27-September 1 | September 3-8 | September 10-15 | September 17-22 | September 24-29 | October 1-6 | October 8-13 | October 15-20 | October 22-27 | October 29-November 3 | November 5-10 | November 12-17 | November 19-24 | November 26-December 1 | December 3-8 | December 10-15 | December 17-22 | December 24-29 | December 31, 2012-January 5, 2013 | January 7-12 | January 14-19 | January 21-26 | January 28-February 2 | February 4-9

Vibration

No elevated vibration levels were recorded during this construction period.

To learn more about how we're monitoring noise and vibration during construction, please see our Noise and Vibration page.

Tenders

Design consultant: Hatch Mott MacDonald, AECOM
Construction contractor: Bot Engineering & Construction Limited

Community Updates

For updates from 2010 or 2011, please see our Communication Materials page.

For more information on the Humber River Bridge (Weston Golf and Country Club), please contact the Weston Community Office at 416-241-2300.

Noise wall Committees GTS Toolkit

Stay in the Know!

Sign up to receive email updates on project information. Subscribe now!

Event Calendar

Check out our Event Calendar to view information about upcoming events.
Find out more...

Contact Us

Georgetown South Project
20 Bay Street, Suite 600
Toronto, ON M5J 2W3
416-406-0489
gts@gotransit.com

Strachan Community Office
901 King Street West, Suite 102
Toronto, ON M5V 3H5
416-581-1300

Weston Community Office
NEW 44 King Street
Toronto, ON M9N 1L1
416-241-2300

WTD Community Office
18 Hook Avenue, Suite 204
Toronto, ON M6P 1T4
416-604-9582
By appointment only